FEMA Should Disallow $82.4 Million of Improper Contracting Costs Awarded to Holy Cross School, New Orleans, Louisiana
Date Issued:
Tuesday, April 14, 2015
Agency Reviewed / Investigated:
Submitting OIG-Specific Report Number:
OIG-15-65-D
Component, if applicable:
Federal Emergency Management Agency (FEMA)
External entity, if applicable:
Holy Cross School
Location(s):
New Orleans, LA
United StatesType of Report:
Audit
Questioned Costs:
$82,360,247
Funds for Better Use:
$0
Number of Recommendations:
1